Sub-Contracting process with Scrap and Few more Examples


Concept:

To work on all these assembly parts/Extra accessories, we need manufacturing unit where we can do all this assembly but its costly and time taking for the preparation and we may have some quality issues, by keeping all this in mind every company would like to go for Sub-contracting process- Which means



Certain companies which will be outsourcing (Giving products to other companies), where they use to work only on this assembly with best quality and take the price for only service.

Examples:

Few of the scenarios with explanation.
1     We have 3 child materials and we need the Parent Material (final product), but we will not assemble or manufacture any tools but for the production/sales requirements we need the final product to be assembled.

we will take the 3 child materials from 3 different vendors and we will maintain a BOM with parent material, after that creating subcontracting order for parent material (BOM will be taken automatically with child materials in components).

Do the GR for all 3 materials, and do the transfer posting for all child materials to vendor through MB1B or ME2O

Now do GR for subcontracting vendor, where you can see movement types 101 and 543.

Child materials

1.      L-shaped metallic plate
2.      Spring
3.      Bolts for fitting

Parent Materials

1.      Metallic plate with full furnished.

Implementing:

·        First, we need to procure the materials which are required to prepare the parent material, here we need to procure L-shaped metallic plate, Spring, Bolts for fitting from the respective vendor.
·        We can create 1 PR, with 3 lines mentioning 3 materials in each line individually with respective vendors or same vendor (based on your requirements)
·        Create PO for above 3 materials and as per the respective quantity and do the MIGO (Goods receipt), so that stock will be stored in the plant premises.
·        Complete all 3 material MIGO as mentioned above
·        Now create a BOM for the parent material, so here BOM is very important for all Parent materials.
·        CS01-Create BOM
·        Enter parent material following with all child materials inside
We are maintaining BOM for-what are the components that required to create a one complete parent material.
·        Now create New PO with Item category L-mention the parent material number, so that automatically child materials will go to Material Data-Components (BOM -we maintained)
·        Now in components we have 3 materials (Child)
·        Al the 3 child materials will go to sub-contract vendor for assembly, to send those materials to vendor we need to perform the movement type.
·        MB1B-stock transfer- we need to transfer the stock of all 3 materials to vendor stock by using the movement type 541,
·        Once the stock is transferred, we can see those stock in MMBE-stock under vendor.
·        Now vendor will deliver the assembled goods to plant and we need to perform the MIGO
·        Perform the MIGO with 101- now the stock should be available in MMBE for parent material
·        Remaining child materials quantity will be 0

     Vendor to vendor material shifting through Subcontracting process:


Scenario: 

We need a parent material which will get from subcontracting vendor and child material from another vendor, the child vendor should send the material directly to subcontracting vendor.
Eg: we would like to order a cell phone battery from child vendor, and he will directly send that battery to subcontracting vendor and subcontracting vendor will deliver the fully furnished phone. We need this to be implement in the SAP.

Step 1: Create a normal PO with cell phone battery and go to the delivery address tab in PO, here you can find SC vendor, check the SC vendor and mention the vendor number in the vendor field.

o   So that SAP will pick the delivery address as vendor address automatically.
o   Now the child vendor will deliver the cell phone battery directly to subcontracting vendor (to view this action in SAP, follow below)
o   Now post the GR for the child material PO, MIGO and mention the PO number and date.
o   Enter the quantity, system will not ask for storage location and tick OK and post the GR.
o   Now check in MMBE (Stock Overview), you can see the material is maintained with vendor.

Step 2:

Now create subcontracting PO for the parent material (Phone) with item category L, as we maintained BOM the components will be taken automatically (Child materials) and delivery address to plant in the PO.

Now process for GR for the parent material and maintain the quantity.


If required explore the parent material with + icon and you can see the child materials maintained with movement type 543.

§  541- Sending the material to the subcontracting vendor stock.
§  543-Consumption of material which is delivered to subcontracting vendor.
§  545-scrap material while consumption or vendor material used for the parent material.

Ordering Material and scrap from the subcontracting vendor:

Subcontracting material with scrap.

As we know when the material is manufactured by the vendor, scrap will generate automatically and few of the scraps will be costly or needs to be moved to plant scrap process, so in this case we need to implement such that vendor should provide the parent material along with the scrap.

E.g.: we are ordering a material of sofa; we procure wood from one vendor to plant and will move that material to subcontracting vendor through 541 and will order a subcontracting order along with scrap.

Step1:

o   Create a normal PO for procuring the wood from the vendor and once we receive that wood to plant(warehouse), we can follow the remaining process as mentioned below.
o   Maintain BOM for parent material, while maintaining we will update child materials with specific quantities, basically it will multiply with PO quantity. So, maintain accordingly.
o   Here for scrap, we are taking the scrap from vendor which are consumed for the child materials. If we want that material to plant, we need to create a new material with the name “Scrap” and maintain in BOM as 1- and save the BOM.


·        Meanwhile create a subcontracting PO with parent material with item category L, where BOM will be taken automatically with 1- quantity and child materials.

·        Now do the goods transfer in MB1B with movement 541, so that stock in the warehouse move to vendor stock and now the subcontracting vendor will perform the manufacturing process of sofa.

·        He will create the sofas as per the quantity and delivers the goods to plant along with scrap.

·        Now do the MIGO with 101 movement and post the sofas quantity and click on + icon in parent material, you will see the child materials with scrap.

·        Child materials – means consumed and will be used for sofas.

·        Scrap+ means waste generated and needs to bring to plant as per the PO.

Now go to MB1B and mention the movement 542, bring back the scrap to plant (SAP stock overview)



Final: if we are procuring one material with subcontracting vendor, we need to go with 3rd example, where we need to process the BOM with -quantity instead of scrap we need to post procuring extra material number.
No need to do 542 movement, where this will be consumed for the parent material.

   Please like and comment if you like the content.








28 comments:

  1. This is really nice post, I found and love this content. I will prefer this, thanks for sharing. 304 stainless steel bolts.

    ReplyDelete
  2. Hello, this weekend is good for me, since this time i am reading this enormous informative article here at my home. Scrap Metal Sydney

    ReplyDelete
    Replies
    1. Thank you
      Please reach out to - Studyuuusapmm@gmail.com for queries

      Delete
  3. This is really EXCELLENT . You made the concept of subcontracting clear.
    One doubt I have you created PIR but never used in the process. Is it mandatory to create PIR? if yes you haven't used PIR eith in PR and PO?

    ReplyDelete
  4. It’s very informative and you are obviously very knowledgeable in this area. You have opened my eyes to varying views on this topic with interesting and solid content. cash for cars

    ReplyDelete
  5. Generally I don't learn post on blogs, but I would like to say that this write-up very pressured me to try and do it!
    Your writing style has been surprised me. Thanks, very great post.
    cash for cars gold coast

    ReplyDelete
    Replies
    1. Thank you
      Please reach out to - Studyuuusapmm@gmail.com for queries

      Delete
  6. I've been surfing online more than 2 hours today, yet I never found any interesting article like yours. It is pretty worth enough for me. In my view, if all webmasters and bloggers made good content as you did, the internet will be much more useful than ever before.
    top cash for cars

    ReplyDelete
  7. Great post. I used to be checking constantly this weblog and I am inspired! Extremely useful information specially the ultimate part :) I maintain such info much. I used to be seeking this particular information for a very lengthy time.
    Thank yyou and good luck.
    cash for cars brisbane

    ReplyDelete
  8. Hello There. I found your blog using msn. This is a really well written article. I will make sure to bookmark it and come back to read more of your useful information. Thanks for the post. I will definitely return.
    car removal brisbane

    ReplyDelete
    Replies
    1. Thank you
      Please reach out to - Studyuuusapmm@gmail.com for queries

      Delete
  9. The tutorial is very helpful for a first timer like me, by the way if you could have given a tutorial on creating a free website, it would have been very helpful for newbies like me.
    Thank you
    cash for cars ipswich

    ReplyDelete
  10. The tutorial is very helpful for a first timer like me, by the way if you could have given a tutorial on creating a free website, it would have been very helpful for newbies like me.
    Thank you
    cash for cars hobart

    ReplyDelete
  11. I would like to thank you for the efforts you've put in writing this website. I am hoping to see the same high-grade blog posts from you in the future as well. In fact, your creative writing abilities has motivated me to get my own blog now ;).
    cash for cars melbourne

    ReplyDelete
  12. Hello Ram,

    I would like to thank you for the efforts. If you don't mind please share me the accounting entries which is hitting for each movement type.

    ReplyDelete
  13. Thank you because you have been willing to share information with us. we will always appreciate all you have done here because I know you are very concerned with our. https://www.scrapmetalsydney.com/copper-recycling

    ReplyDelete
  14. To find qualified and dependable home improvement specialists, check with friends, business associates, and neighbours for recommendations. Always get at least three references, and check them out thoroughly. crawl space cleaning sammamish

    ReplyDelete
  15. We buy cars for cash in Victoria and pay as high as up to $9,999 cash in return for all makes and models and nd a free car removal service | Address:13 Gay St, Benalla VIC 3672, Australia | Phone: 041 231 5595 | Cash For Cars Melbourne

    ReplyDelete
  16. Cash for Car Brisbane is an online service that allows people. You are one call away far to cherish this amazing service. Moreover, Cash for Car Brisbane deals in the spare parts of the car at a cheap amount. You can get your desiring automobile parts of high and best quality at your doorstep | Address: 103 South Pine Rd, Chermside QLD 4032, Australia | Phone: 07 3359 8688 | Cash For Cars Brisbane

    ReplyDelete
  17. In North Brisbane We are committed to being Brisbane’s fastest, easiest way to get cash for a junk or unwanted car Cash For Cars North Brisbane

    ReplyDelete
  18. Our top-quality car removal Logan service also free on-site inspection of your vehicle and no added cost or charges for car towing as well | Address: 135 Bradman St, Acacia Ridge QLD 4110, Australia | Phone: 0423514111 | Email: info@apluscarremoval.com.au | Car Removal Logan

    ReplyDelete
  19. Well known work, its a general substance. It makes for me social gatherings of enjoyment and intrigue. Visit us at Cash For Car

    ReplyDelete
  20. Boundless work and keep on sharing.thanks for this post please share more post in this way. Car Removals Sydney offers top dollar for your unused vehicles.

    ReplyDelete
  21. Very informative post! There is a lot of information here that can help any business get started with a successful social networking campaign. Rubbish removal wolverhampton

    ReplyDelete

Featured post

What is IDOC? Explanation for Interview Purpose

What is IDOC? Explanation for Interview Purpose: Overview Explanation for Interview purpose Question: What is IDOC ? IDOC i...

Popular Posts