ERS/Auto PO process through Inventory Management
and Source Determination-SAP MM
For Videos Explanation, please go to YouTube and Subscribe - Studyuuu SAPMM
For Videos Explanation, please go to YouTube and Subscribe - Studyuuu SAPMM
Inventory management Concept:
Concept:
we all know that in procurement
-SAP, Purchase requisitions/Orders will be created automatically. One of the
process is MRP, but here we discuss about only purchase orders which will be
created automatically by inventory management process and Source determination
process
.
Here we
mainly discuss on 2 factors, how the PO will be created by inventory method and
requirement.
Requirement:
Many cases clients will not request to create a purchase order especially in
terms of inventory, they will be receiving the goods from the vendor as a
monthly contract with vendor-Not official contract, as per the requirements and
urgency stakeholders will be ordering directly from the vendor without purchase
order and in this cases we need PO for the payment purpose. PO is the mandatory
document for posting or paying the invoice. So, after receiving the goods GR
needs to be posted and requirement is like while posting GR- the SAP should
create a PO automatically as per the GR data mentioned by stakeholders.
To possible
the above requirements we need to make and assign few settings in our system,
so that requirement will get possible to do this.
Requirements:
Material- While posting GR- we will be
entering the material and every material there will be a purchasing tab which we
can maintain the auto PO filed check – which is mandatory for auto PO process.
Vendor- every purchase order contains a
vendor and if a PO is creating automatically then that should be with vendor
and vendor -purchasing view also contains auto PO option, through which we need
to select the option for the further process.
If you are
maintain auto PO for 100 materials with 50 vendors then all the materials and
vendors should contain this settings in master data to create PO’s
automatically, you can use MASS option to update the data for 100 materials and
50 vendors at one time.
PIR- Mandatory, though we are creating
PO automatically its good to create PIR manually because PO should pick the
price automatically without any interruption, if not while doing
MIGO/MB01-system will popup the error to maintain the price- always price in PO
will be taken from PIR and PR price will be taken from material master.
Back end
settings to make auto PO-
Along with
the front-end settings, we need to make few back-end settings lines which
document type should be created automatically and what are movement types needs
to be supported for auto PO’s.
These
settings will be always available in the backend and not in front end.
Setting 1:
SPRO-
Materials Management-
Purchasing-
Define
default values for Document types-
Here we
need to define the T-code in which system should be accept the auto PO’s and
what is the order type it should create while creating.
To maintain
these functionalities, it’s a setting to be done in purchasing tab.
Setting 2:
SPRO-
Materials Management-
Inventory-
Goods
receipt-
Create
PO automatically-
Here we
need define the movement types 101 and 161, where 101 is for Goods receipt for
normal order and 161 is for return order for the vendor.
In these
settings will define the two movement types and maintain the auto PO selection
for both, then based on the movement type we enter system will choose to accept
it that auto PO will be created based on the input.
Process:
Let’s think
you have received the goods to plant without purchase order based on the
request from stakeholder and now we need to maintain the invoice in the SAP for
that we need to create PO but here auto PO should work.
Now we know
the quantity and the vendor we received from and we made backend and front-end
settings for the above scenario to work.
Now go to
MB01- mention the movement type, plant and system will check for movement type
settings and show the popup of auto PO creation and once enter we need to
maintain the material/vendor/storage location/quantity and just execute, so
that system will enter the next screen and it will pick the price from PIR and
will be saved in the next screen.
Once this
step is completed, system will create PO automatically and you can check by
going to ME2L by entering material and vendor.
We have
successfully created the auto PO process through inventory.
Source Determination for Auto PO-
Concept
Above we
have learnt the auto PO process through inventory and now this process teaches
through source determination.
We all
creation of PO takes more time because it should go for many approvals and its
time taking process but we cannot stop the production because of approvals, so
for that there is an exception for particular materials with specific vendors,
we can make those materials and vendors for auto PO process, so that only for
those materials it’s possible to create auto PO from only from those vendors
which we are maintained as auto PO check option.
In this
process stakeholders will just create the PR’s with source of supply vendor-
Where the vendor number will be updated automatically and how and all will be
explained below.
Once
everything is updated in PR’s then we can create auto PO’s at a time and its
very easy to execute all at a time and SLA and approvals will be not determined
for this type of processes.
Requirements:
Material- If we are creating auto PO then material master
-purchasing view auto PO option needs to be selected as a mandatory field and
vendor master purchasing view should be checked with auto PO tab and PIR is
mandatory as a source and vendor will pick in PR automatically.
Once everything is ok then PR will be created for process
further.
Material:
Material master purchase view should be checked
Vendor: vendor
master purchasing view auto PO should be checked
PIR: PIR
is mandatory for the purpose of source of supply purpose and price purpose
Back end
settings to make auto PO:
There is no back-end settings for Auto PO
with source determination, but we can maintain source list if we have many
vendors for that material.
Process:
Once everything is maintained like material, vendor, PIR
then PR should be created with source determination check which will be
available in the top of the screen.
Once that check is done then enter the material, quantity,
plant and purchase group and press, so that vendor will be picked automatically
in the PR vendor tab.
To process auto PO – go to ME59N and enter the material and
vendor, so that it will show all the open orders for that vendor and just
execute all the PR’s, so that PO will be created automatically.
ERS-
Evaluated Receipt Settlement
ERS is a method where several companies and vendors will
prefer because of fast payment transactions to the vendors from APAY side and
few of the exceptions and advantages are there for ERS.
Before vendor entering ERS, there is process of concept
where vendor will send the goods as per the PO copy, but he will not send the
invoice after the goods delivered.
The requester will post the GR and system will post the IR
with respect to GR and PO, ERS explains Invoice will be posted automatically
once the GR is posted and payment will made as per that fastly.
Normally this is the duty of Accounts payables to run the
MRRL to post the invoices automatically as per the GR and PO and if they are
issuing any errors while posting then SAP MM consultant will come into picture
to resolve the issues.
Mandatory settings:
Vendor master should contain Autoevaulated GR Del ERS tab
and Autoevaulated GR Settlement along with GR based invoice.
We need to select all the 3 tabs, so that while creating
PR/PO ERS tab will popup in the invoice screen and the vendor is eligible for
ERS payment method.
We can find those above settings in vendor master
-Purchasing tab and its mandatory for the selection of process.
PIR is optional and if we maintain price will pick from PIR
or else we need to maintain manually.
PR should be created and check in invoice screen ERS is
popping up or not, and if not popping then check the vendor master settings and
if everything id ok then create a PO.
Here PO is created as per the PR and Tax code is mandatory
in PO because tax will be calculated automatically and where invoice will post
automatically as per that.
Payment terms is mandatory in PO while creating ERS PO,
because its payment related and here everything is automatic, so for being that
payment terms and tax code is mandatory in PO.
Once the PO is created maintain the GR, Where GR will be
posted manually and with respect to PO.
Once GR is done to post the invoice automatically, we need
to run the MRRL screen, where you need to select the material or vendor for processing
the automatic invoice.
Once this is done, IR will be created in all the PO’s and
with respect to GR.
Now with respect to payment terms payment will be made to
vendor and we can check the status in FBL1N.
Small Concept
for GR:
Under tolerance and over tolerance can be adjusted while
doing MIGO, Normally if we order PO for 100 quantity for that we need to post
100 as GR but incise if we received 110 then what’s the procedure, and lets
think you need that extra 10 quantity also.
This scenario is quite often to receive in any plants, once
they receive go to PO and delivery tab and maintain the over tolerance quantity
as 10%, so that GR we can post for 110 quantity and after we can change quantity
in PR/PO.
Scenario 2:
Let’s think we don’t want to receive the
less quantity then ordered quantity in PO, then we can make these settings in
PO that under tolerance acceptance, maintain as 0% tolerance so that MIGO
should be posted with full quantity as ordered in PO.
Please let me know any concept in required
to post, currently I’m writing blog for Account Determination
Kindly like and comment on the blog if you like the content.
sir can u expalin over tolerance and under tolerance in sap MM.It has been asked in the interview
ReplyDeleteCheck out YouTube--Studyuuu sap MM
DeleteI have posted all videos there
Thanq for sharing the knowledge, I have a doubt.
ReplyDeleteOver del. Tolerance is 10%, PO Qty - 100 and GR posted for 110.
After that do we need to modify the qty in PO?
2. without changing the qty in PO, what is the procedure?
Yes you can modify the PO
ReplyDeleteExcellent and very exciting site. Love to watch. Keep Rocking. https://autopartsgh.com/
ReplyDeleteThank you
DeletePlease reach out to - Studyuuusapmm@gmail.com for queries
An auto fix portable repairman is in obviously better situation to offer a lot for their administrations. Best Covers for Car Seats
ReplyDeleteThank you
DeletePlease reach out to - Studyuuusapmm@gmail.com for queries
Thank you
DeletePlease reach out to - Studyuuusapmm@gmail.com for queries
Today, Toyoto are the world's greatest vehicle organization as per ongoing business sector gauges. Best Covers for Car Seats
ReplyDeleteThis is such a great resource that you are providing and you give it away for free. I love seeing blog that understand the value of providing a quality resource for free. sklep samochodowy szczecin
ReplyDeleteThank you
DeleteStudyuuusapmm@gmail.com
Thank you
DeleteStudyuuusapmm@gmail.com
Free Wireless Credit Card Machine advertising has bombarded consumers so heavily words like Quality, Reliability and Trust have become completely meaningless. For automotive repair facilities, who long ago hung their hats on such concepts, now is the time to focus on becoming a communicator and information source rather than jut another huckster in the crowd.
ReplyDeleteHello There. I found your blog using msn. This is a very well written article. I will be sure to bookmark it and return to read more of your useful info. Thanks for the post. I’ll certainly comeback. Mega888 apk download
ReplyDeletePretty good post. I just stumbled upon your blog and wanted to say that I have really enjoyed reading your blog posts. Any way I'll be subscribing to your feed and I hope you post again soon. Big thanks for the useful info. auto czesci szczecin
ReplyDeleteOne of the manners in which that an auto insurance agency will vie for your business is through auto protection rates. white label warranty
ReplyDeleteUsed tractor tires come in all different sizes. From super large tires to reasonably small tires it all depends on the tractors they come off. A tire is considered used as soon as the tractors wheels turn. tractors for sale UK
ReplyDeleteAwesome dispatch! I am indeed getting apt to over this info, is truly neighborly my buddy. Likewise fantastic blog here among many of the costly info you acquire. Reserve up the beneficial process you are doing here. 2020 Keystone RV Fuzion 410
ReplyDeleteI just thought it may be an idea to post incase anyone else was having problems researching but I am a little unsure if I am allowed to put names and addresses on here. 2021 Winnebago Micro Minnie 2306BHS
ReplyDeletePallet racking helps to increase the productivity and functionality of factories and warehouses. You must know the various types in which they are available to pick the best one for your business. plastic pallets
ReplyDeleteI’m impressed, I have to admit. Genuinely rarely do I encounter a weblog that’s both educative and entertaining, and without a doubt, you may have hit the nail within the head. Your idea is outstanding; the thing is an issue that not enough consumers are speaking intelligently about. My business is delighted that I stumbled across this within my search for some thing in regards to this. Gambling and Casino SEO Backlinks
ReplyDeletePurchase order management best practices Thanks for a very interesting blog. What else may I get that kind of info written in such a perfect approach? I’ve a undertaking that I am simply now operating on, and I have been at the look out for such info.
ReplyDeleteThere are likewise signs which mark public landmarks and public parks, just as state stops, and focal point signs. traffic management plans
ReplyDeleteWindshield fix is economical contrasted with windshield substitution. Fix disposes of issues related with substitution, for example, spilling, wind whistle or windshield disappointment due to airbag organization.auto glass repair near me
ReplyDeleteThere are a few motivations behind why the quantity of windshield chip fixes and break fixes have expanded in the course of the most recent couple of years.auto glass repair
ReplyDeleteauto glass replacement
Windshield fix is reasonable contrasted with windshield substitution. Fix takes out issues related with substitution, for example, spilling, wind whistle or windshield disappointment due to airbag arrangement. https://www.cprautoglassrepair.com
ReplyDeletewww.cprautoglassrepair.com
Looking for auto windshield substitution isn't simply a restorative move. You are legitimately expected in many states to keep up with your windshield in great condition.cprautoglassrepair.com
ReplyDeleteclick here
I appreciate you sharing this blog. Much thanks again. Want more.
ReplyDeletebest management training
Thanks a lot for the blog article. Really thank you! Want more.management training in singapore
ReplyDeleteThese are for the most part looking like a star, bullseye, or small break. Despite the fact that it might seem harmless, over the long haul, a stone chip will without a doubt spread to shape a break.windshield crack repair
ReplyDeleteAn all out arrangement stage can involve different management modules that can be assembled to exactly work successfully to meet complex investments.
ReplyDeleteex-ponent.com
Amazing article, keep posting such interesting content, and I acknowledge your commitment to this informative blog.
ReplyDeletesoftware development company
An all out investment management arrangement stage guarantees a legitimate usage of key qualities from engineering to working highlights for a financially savvy management of investments that fulfill business needs.
ReplyDeleteExponent Investment Management
The software assists in developing risk mitigation strategies and action plans. It allows users to assign responsibilities, set deadlines, and track the progress of risk mitigation activities. Risk Management Software
ReplyDeleteReinsurance allows insurance companies to share the risk of large losses with other insurers.
ReplyDeleteDirect Insurance Gainesville
"If your car is vibrating at high speeds, it could indicate a problem with your tires." mechanic gold coast
ReplyDelete